Subject
Responsibility
Cooperation-
project
Realization |
"Tiryns" Mycenaean Citadel on the Peloponnese
- in 1991/92 conception-studies for conservation
- since 1997 planning and execution of a long term conservation
and rehabilitation programme of the archaeological site in total
finished:
- central palace-area, late mycenaean staircase
- western monumental staircase, “Mittelburg” access
- renewal of staircase to western gate + the ”Unterburg”
- stabilization of cyclopic walls “Oberburg” Westside
- stabilization-programms of cyclopic UB-walls west
- large protection- and conservation-programme of the 1980ies DAI-excavation in “Unterburg”
- early Helladic Central Building, mudbrikprotection
work in progress:
- Tower, Ramp, Galeria East
architect and technical projectleader
FRG: Deutsches Archäologisches Institut, DAI Athen,
University of Heidelberg, Institut für Ur- und Frühgeschichte
Greece: Ministry of Culture Athen, Ephoria of Antiquities Nafplion
EU-Com: Financial Contribution Programme
UNESCO: Entry in the List of Worldheritage
1997 - 2005, ongoing |